EC clearance received for Delhi-Saharanpur section of SH-57

The 19th meeting of the Empowered Committee (EC) chaired by Secretary, Department of Economic Affairs has recently accorded final environment clearance for four laning with PSS of Delhi-Saharanpur section of SH-57 on DBFOT (Toll) basis.The Government of Uttar Pradesh is the sponsoring authority for this project. The project comprises four laning of 206.089 km road stretch. The total project cost is Rs 1,718.35 crore. The viability gap funding for this project is Rs 343.53 crore. SEW - Prasad Consortium Infrastructure Ltd, Hyderabad is the project developer. The concession agreement was signed on 1st August, 2011. Independent Engineer was selected, agreement signed on 28.02.2012. The developer has started work and completion is targeted by 16th September 2014.
 