Four laning of Varanasi-Shaktinagar road gets final EC clearance

The 19th meeting of the Empowered Committee (EC) chaired by Secretary, Department of Economic Affairs has recently accorded final environment clearance for four laning of Varanasi-Shaktinagar road of SH-5A in Uttar Pradesh.The Government of Uttar Pradesh is the sponsoring authority for this project. The project comprises four laning of 117.60 km road stretch. APCO Chetak - Patel Ltd, Lucknow is the project developer. The project was awarded on 15th November, 2011. The concession agreement was signed 8th December, 2011. Forest clearance NOC has been obtained from Government of India. The total project cost is Rs 1,211.96 crore. The viability gap funding for this project is Rs 241.92 crore. The completion is targeted by 18th September, 2015.
 