Construction World - Indian Edition | June 2009

  Arbitration

Debate Over Delay

JANAKI KRISHNAMOORTHI presents the ninth in a series of case studies referred for arbitration

In December 2001, the owner and developer of a plot in a Mumbai suburb entered into an agreement with a civil contractor to construct an office building in Mumbai with an approximate built-up area of 125,000 sq ft. The project was to be completed in November 2002.
According to the stipulation of Brihanmumbai Municipal Corporation (BMC), the contractor was to be paid construction cost at Rs 771 per sq ft of built-up area with the area defined in the contract as sanctioned FSI, air-handling units (AHU), staircase, lift area, lift machine room and basement. Elevation features, duct voids, underground/ overhead water tanks, pavement, security cabin, electric substation, meter room and common toilets were to be provided by the contractor without charging anything extra. The owner appointed two architects and an RCC consultant for planning, preparing drawings, complying with formalities and supervising the project.

Contract terms
The following were the other major terms of the contract:
• The contractor had to submit monthly bills through architects who would certify them within a week and the owner was to make payments within a week of such certification.
• While making payments, the owner had to deduct retention money (RM) of 5 per cent, pay 50 per cent of billed amount by cheque and in lieu of the balance 50 per cent allot galas along with one open car parking space per gala to the contractor, calculating the value at Rs 3,821 per sq ft of saleable area.
• After obtaining the occupancy certificate (OC), the contractor could retain, transfer or sell the premises. If the market price of the saleable area exceeded Rs 3,821 per sq ft, the contractor could retain the profit. But in the event of market price decreasing, the owner would reimburse the loss without interest.
• If payments were delayed beyond two weeks of certification, the contractor would be entitled to 18 per cent per annum interest on the unpaid amount till it is paid.
• The project had to be completed within 11 months from the date of the agreement, failing which the contractor would be liable to pay compensation to the owner at 1 per cent of the contract value per month, limited to 5 per cent of the contract value to be worked out as agreed.
• If the contractor failed to adhere to the agreed work schedule, the owner could terminate the agreement if the breach was not remedied within two weeks of notice.

Points of dissent
Differences and disputes surfaced between the owner and the contractor over delay in executing the project, changes made in design and consequent deferred issue of drawings, project period extension, certification and payment of bills, and allotment of premises as agreed to the contractor. Both parties nominated their own architect to jointly settle the quantum of work completed and payment issue. Based on drawings, the architects calculated the completed work area and the payment due to the contractor. The owner, however, did not agree with the decision and asked them to reduce the area. The architects declined to comply but soon after the architect nominated by the owner unilaterally estimated the dues to the contractor. But the owner did not pay even this amount and the contractor also declined to accept this. In January 2003, the contractor invoked arbitration.

Arbitration
The arbitral tribunal comprised two co-arbitrators with Dr Kirty Dave representing the contractor (claimant) and a retired high court judge representing the owner (respondent). Yet another retired high court judge was appointed as the presiding arbitrator. Both parties were represented by an advocate
and a techno-legal consultant. The preliminary meeting of
the tribunal was held on
April 23, 2003.
The respondent raised preliminary objections over the claimant’s right to invoke arbitration as it alleged that the latter’s partnership firm was not properly registered under The Indian Partnership Act of 1932. It also questioned the validity of claims put up under the signature of one Vipul Shah who it claimed was not the legally constituted representative of the claimant. After examining the documents produced
by the claimant, the tribunal overruled the objections.

The claimant’s
contention
While the work was in progress, the respondent made a change in the construction design, from the originally agreed ‘beam slab’ to a ‘flat slab’. The claimant alleged that this change in design and deferred issue of drawings caused the delay in executing the project. And the respondent’s refusal to grant more time amounted to a cardinal breach of contract and there was no provision in the agreement by which the respondent could close the agreement before the project’s completion. The claimant also maintained that the respondent defaulted in making the payment as per the agreement.
The claimant submitted eight claims, including those for non-payment of bills, work completed, loss owing to sudden closure of contract, loss of profit on work unexecuted owing to sudden stoppage, loss owing to non-allotment of galas, delay damages, interest on award amount, and cost of arbitration. The claimant also argued that as the respondent was responsible for the delay, refused to grant justified time extension and defaulted in making the payment, it could not demand any compensation.

The respondent’s representation
The respondent, however, held the claimant responsible for the delay, alleging that despite handing over the site early and issuing all plans and drawings on time, the claimant failed to mobilise resources on time and complete the work according to schedule. It declared that payments were generally made in advance to the contractor and even prior to the architect’s certification, and argued that only some of the bills, which were incorrect and uncertified, had not been paid.
In turn, the respondents submitted six counter claims, including those for compensation owing to delay in completion of work, loss owing to delay in construction and enhanced cost of construction and loss owing to marketing and publi-
city expenses.

Interim award
The claimant submitted an application in August 2004 requesting for an injunction restraining the respondent from transferring, letting out or in any other way creating third party rights with respect to the 24,165.29 sq ft of the property that was to be allotted to it in lieu of payment as per the contract. The respondent’s advocate, however, agreed not to sell or dispose of only 14,000 sq ft of the property and the tribunal accordingly passed an interim order.
Finally, the respondent and claimant reached a settlement on the issue in April 2006 whereby the respondent agreed
to execute an agreement for sale of
1,660 sq ft of the property in favour of the claimant. Both parties also reached a consent agreement on the quantity of work done and on two claims regarding payments against pending bills.

The final decision
After examining the documents and listening to oral evidence and the legal representatives of both parties, the tribunal arrived at the following key conclusions:
• The respondent failed to provide reasonable facilities for completing the project on time.
• Changes effected in design (from beam slab to flat slab) and the time of issue of drawings necessitated the need for more time to execute the project.
• Not extending the time for completing the project was unfair on the part of the respondent.
• The claimant was deprived of the contractual right to complete the work and gain business profit and hence it was entitled to payment for work done and had to be compensated for loss owing to unexecuted balance work.

The ruling
The tribunal accepted the following claims of the claimant:
• Loss of profit on the work it was prevented from executing owing to sudden stoppage of work by the respondent: The tribunal ruled that as a settlement had been reached for work done and on bills raised, the only element of loss of profit could be considered on balance cost of work and awarded an estimated sum along with loss of profit at
10 per cent owing to termination of contract.
• Interest on award amount: The tribunal ruled that no interest was payable against two claims settled by mutual consent and awarded 10 per cent interest on only one claim for loss owing to stoppage of work from the date of the preliminary meeting of the arbitral tribunal (23.4.2003) till payment.
All other claims were rejected by the tribunal because they were based on assumed figures, not backed by concrete details and analysis, or overlapping with other claims.
The tribunal rejected all the counter claims of the respondent as all of them were based on project delay attributable to the respondent. The tribunal ruled that the respondent also committed breach of contract by not extending the time to complete the project.
The tribunal ruled that arbitration cost should be borne by both parties but the respondent should also bear the claimant’s share of the arbitrators’ fee.

In a Nutshell

Type of project: Office complex
Location: Mumbai
Agreement executed:
December 2001
Arbitration invoked: January 2003
Parties in dispute: Plot owner/developer and civil contractor
Arbitral tribunal: Dr Kirty Dave
co-arbitrator, nominated by claimant, and two retired high court judges; one representing the respondent
and the other nominated as
presiding arbitrator
Parties represented by: Advocates and techno-legal consultants
Preliminary meeting of tribunal: April 2003
Duration: Four years
Award declared: June 2007

Arbitrary Laughs
(Conceived by Dr Kirty Dave)

Q : What is the difference between litigation and arbitration?
A : A five-star hotel bill.

Q : Why do we need joint arbitrators?
A : So they can sleep by turn.

Respondent : Sir, shall we go in for extension of time?
Arbitrator : I don’t mind as long as the escalation formula of contract is applicable to my fees.

Respondent : We had to reduce the rate as the contractor did not cure the concrete and we had to do it.
Arbitrator : But why did you allow him to lay concrete that required to be cured later on?

Claimant : For brickwork, they changed bonds, leading to lot of breakages.
Arbitrator : I know when bonds are broken; they create rights and liabilities.

Arbitrator : Tell me in brief what created the dispute.
Claimant : Only ‘piles’ [meaning pile foundation], sir.
Arbitrator : You should have gone to a surgeon in time.

Arbitrator : Did you suffer such huge losses in this contract?
Claimant : Not exactly, but my techno-legal advisor convinced me I had.

Dr Kirty Dave
The details of this case have been provided by Dr Kirty Dave, co-arbitrator in the case, who has handled several arbitration cases as an arbitrator and a techno-legal consultant. An arbitrator on the panel of the American Arbitration Association, he is also Chairman, Law and Arbitration Committee of Builders’ Association of India; National Vice-President of the Indian Institution of Technical Arbitrators; Vice-President, Indian Council of Arbitrators; and elected representative of the council’s governing body. A graduate in engineering and law, Dr Dave acquired his doctorate in engineering law from the US. He served as a Class I officer in the Government of India and has been an engineering consultant to Iran and Oman, and a techno-legal consultant to the US Government, Brihanmumbai Municipal Corporation, and many leading national and international firms. The first Indian engineer to be invited by the US as a ‘Citizen Ambassador for Construction Management’, he teaches construction law at the postgraduate level, besides being an adjunct professor to the Indian Institute of Technology - Mumbai.
You can contact Dr Dave on Tel: 022-26609991 or
E-mail pspe@technolegal.org

Dr Kirty Dave’s views on…

Appointment of arbitrators
As our Arbitration Act does not specify who can be an arbitrator, you can name your Chinese wife or even your business partner as an arbitrator in your own case. If someone questions an arbitrator’s neutrality in a case, the decision would be taken by the same arbitrator himself and cannot be challenged in court. You can only challenge the award but by then many years would have gone by. Further, several government and public-sector organisations do not allow the claimant to select his own arbitrator. The co-arbitrator and the presiding arbitrator have to be chosen from the list sent by them.

Arbitral proceedings
These have become an alter ego of the courts with the entire court culture being imported into the process. The Code of Civil Procedure and the Evidence Act, which are not applicable, have made their entry through the back door and the latter is being used recklessly to delay proceedings. The construction business is hugely documented and all arbitrators have to do is to study and understand the documents, apply the standard questions and law, and arrive at a decision. Oral evidence is hardly necessary and yet many arbitrators encourage it. Thus, cases get prolonged with each sitting costing nothing less than Rs 3 lakh to Rs 4 lakh. Can we afford this? We are also losing out on our international reputation as many people shy away from initiating arbitration proceedings in India.

False claims
In the construction industry, false claims are aplenty and those who file them get away without being penalised. For instance, an American design company that raised a claim for its unpaid fee against a municipal corporation ended up defending a false counter claim of Rs 1,800 crore! Ultimately, the shocked American firm gave up its claims and agreed to a settlement. In the US, the corporation would have been sued for false claims and been made to pay a heavy penalty under the False Claim Act (FCA). It is time we also introduced a mechanism like FCA. Apart from saving time and money consumed on such false claims, we would also prevent the greater risk of such claims being awarded.

Unfair contract terms
Many contracts in India, particularly those drafted by the government and public-sector units, have clauses that are internationally considered unconscionable (unfair or violating the fundamental law of the society) or illusory (not binding yourself but binding the other side). Clauses like ‘no compensation for delay whatsoever’ and ‘this work in part or as a whole can be withdrawn without assigning any reason’ fall under these categories. A contractor who prepares to execute a project reaches the site only to be driven out soon after by the employer without any compensation because the project was shelved. And the contractor faces the situation because he signed a contract with clauses over which he had no say. Unfortunately, our law does not recognise the existence of unconscionable or illusory clauses. In India, courts believe that once you sign a contract, executing it is your responsibility irrespective of whether the document you signed is executable or not.

Encashment of bank guarantee
Contractors generally assure performance through a bank guarantee that can be encashed by the employer even upon his assuming that the contractor has failed to perform. The employer need not prove breach of contract. How can the employer be the judge in his cause? Many companies have been completely paralysed owing to such encashment. This is yet another area that needs to be looked into. I believe that if the three situations enumerated above – conflict of interest, bank guarantee and unconscionable process – are taken care of in drafting, sanctioning or endorsing a contract, the construction industry will benefit immensely.




 

[1] [2] [3] [4] [5] [6] [7] [8] [9] [10] [11] [12] [13] [14] | Next | Home

© COPYRIGHT 2008 All Rights Reserved www.constructionupdate.com